Portal BASE · ID 1180444

174 days between signing and publication

Águas do Noroeste, S.A.Execução da empreitada denominada AR 2108 - EMPREITADA DE EXECUÇÃO DO SISTEMA ELEVATÓRIO DE ANTAS, no âmbito do Sistema Multimunicipal de Abastecimento de Água e de Saneamento do Noroeste.

Who contracts with whom?

BuyerÁguas do Noroeste, S.A.NIF 509436595
Recorded contract value654,573.00 €legacy reported value

These are contract records, not verified payments or an estimate of money received by each supplier.

  1. Signed
  2. Published

174 days between the recorded signing and publication dates.

Dates are displayed in recorded chronological order. A gap alone does not establish a breach of law.

What deserves a closer look

Reporting leads

174 days between signing and publication

Signing is recorded on 2014-03-12 and publication on 2014-09-02, an interval of 174 days. Recorded dates may need correction; this calculation does not establish a legal breach.

Question for the public body

What explains the gap between the recorded signing and publication dates?

Documents and records to verify

Check both dates against BASE and the signed contract. Ask when the record was submitted and whether it was corrected.

This observation does not establish favouritism, illegality or loss. Verify the documents and seek the public body’s explanation before publishing.

The recorded price fields

Base price / estimate
840,000.00 €
Contractual price
Not available
Reported final price
654,573.00 €

Values describe contracts, not losses or verified payments. Missing values are not treated as known spending.

Some older records combine contractual and final values. This limitation remains visible until reimport. These are not verified payments.

Main suppliers

Supplier totals use published shares; where unavailable, equal allocation is an estimate.

Contract Details

Procedure
Concurso público
CPV
45232411
Contract Type
Empreitadas de obras públicas
Location
Portugal, Braga, Esposende
Publication
2014-09-02
Celebration
2014-03-12

Data coverage

Source evidence: Portal BASE · Not available

essential fields present: 4 (5)

Missing fields: contractual price

Not available

Risk Flags

An indicator describes a pattern in the data. It does not establish wrongdoing. No indicators does not certify a contract.

A2 · Late Publication

Publication is more than 10 calendar days after signing. This configured delay is not a legal deadline determination.

Source evidence
Rule
A2/A3 late publication: 174 days after signing (threshold: 10)
Publication Date
2014-09-02
Signing Date
2014-03-12
Days Late
174

A2_PUBLICATION_AFTER_CELEBRATION · HIGH · 2026-03-06 · Not available