Escola Básica e Secundária Armando Côrtes-RodriguesAjuste Direto por lotes n.º1/2025 - Aquisição de serviços regulares especializados de transporte Coletivo
Signing is recorded on 2025-03-05 and publication on 2025-03-27, an interval of 22 days. Recorded dates may need correction; this calculation does not establish a legal breach.
Question for the public body
What explains the gap between the recorded signing and publication dates?
Documents and records to verify
Check both dates against BASE and the signed contract. Ask when the record was submitted and whether it was corrected.
The supplier’s identification is incomplete
The record names no supplier, or one supplier has no tax identifier. This describes incomplete data, not the absence of an award recipient.
Question for the public body
Which supplier and tax identifier appear in the original contract, and why are they missing from the record?
Documents and records to verify
Open the contract and award documents. Ask the public body to identify the recipient and correct or explain the missing fields.
This observation does not establish favouritism, illegality or loss. Verify the documents and seek the public body’s explanation before publishing.
Values describe contracts, not losses or verified payments. Missing values are not treated as known spending.
Some older records combine contractual and final values. This limitation remains visible until reimport. These are not verified payments.
Main suppliers
Not available
Supplier totals use published shares; where unavailable, equal allocation is an estimate.
Contract Details
Procedure
Ajuste Direto Regime Geral
CPV
60120000
Contract Type
Aquisição de serviços
Location
Portugal, Região Autónoma dos Açores, Vila Franca do Campo
Portugal, Região Autónoma dos Açores, Vila Franca do Campo
Portugal, Região Autónoma dos Açores, Vila Franca do Campo
Portugal, Região Autónoma dos Açores, Vila Franca do Campo
Portugal, Região Autónoma dos Açores, Vila Franca do Campo
Publication
2025-03-27
Celebration
2025-03-05
Data coverage
Source evidence: Portal BASE · Not available
essential fields present: 3 (5)
Missing fields: contractual price, suppliers
Not available
Risk Flags
An indicator describes a pattern in the data. It does not establish wrongdoing. No indicators does not certify a contract.
A2 · Late Publication
Publication is more than 10 calendar days after signing. This configured delay is not a legal deadline determination.
Source evidence
Rule
A2/A3 late publication: 22 days after signing (threshold: 10)
Publication Date
2025-03-27
Signing Date
2025-03-05
Days Late
22
A2_PUBLICATION_AFTER_CELEBRATION · HIGH · 2026-03-06 · Not available
C1 · Missing Supplier NIF
A recorded supplier has no NIF, or a positive reported final price has no recorded supplier. This describes source completeness.
Source evidence
Rule
C1 no winner recorded: awarded contract (effective price > 0) has no supplier identified
C1_MISSING_WINNER_NIF · MEDIUM · 2026-03-06 · Not available
Experimental indicators and advanced analysis
A9 · Abnormal Price Reduction
Reported final price is below half the positive base price. A reduction is descriptive and requires source review.
Source evidence
Rule
A9 price reduction: ratio 0.3138 outside [0.5, 1.5]
Base price
3760.0
Total effective price
1180.0
Ratio
0.3138
A9_PRICE_REDUCTION · LOW · 2026-03-06 · Not available