Município de Vila Nova de GaiaEstaleiro; Demolições; Demolição de pavimentos em betão betuminoso; Pavimentação / faixa de rodagem; Regas de impregnação e de colagem; Pavimentação com misturas betuminosas na faixa de rodagem; Sinalização horizontal e vertical; Drenagem de águas pluviais; Construção de sumidouros; Nivelamento de tampas.
Signing is recorded on 2024-05-14 and publication on 2024-06-07, an interval of 24 days. Recorded dates may need correction; this calculation does not establish a legal breach.
Question for the public body
What explains the gap between the recorded signing and publication dates?
Documents and records to verify
Check both dates against BASE and the signed contract. Ask when the record was submitted and whether it was corrected.
This observation does not establish favouritism, illegality or loss. Verify the documents and seek the public body’s explanation before publishing.